Construction Update - January 15 and 17, 2019 **UPDATE**

Limonite Progress Schedule 

Contractor will be working on construction stages 1C. Field activities will consist of bridge construction, roadway excavation for ramps, retaining wall excavation, and Limonite Avenue road work.

Lane and Ramp Closures

Contractor will be closing ramps and Limonite Avenue Bridge on Tuesday and Thursday, January 15 and 17, 2019. The closures on Thursday January 17, 2019 will only be used if the work is not completed on Tuesday.

*UPDATE* Closures will not happen tonight, January 15 due to rain. Contractors will complete their work on Thursday, January 17 if it does not rain on Thursday.

Schedule

Tuesday and Thursday nights, January 15 and 17

9 p.m. to 5 a.m

Closure

Full closure of Limonite Avenue Bridge

Full closure of all ramps

Construction Update - Week of January 6 - 12

Limonite Progress Schedule 

Contractor will be working on construction stages 1C. Field activities will consist of bridge construction, roadway excavation for ramps, retaining wall excavation, and Limonite Avenue road work.

Lane and Ramp Closures

Contractor will be closing ramps and outside lanes of the I-15 Freeway on Monday and Tuesday, January 7 - 8, 2019.

Schedule

Monday night, January 7

9 p.m. to 6 a.m

Tuesday night, January 8

9 p.m. to 6 a.m

Closure

NB and SB I-15 closure outside lanes

Full closure of all ramps

NB I-15 closure of outside lane

Full closure of NB ramps

Construction Update - Week of December 2 - 8

Limonite Progress Schedule 

Contractor will be working on construction stages 1C. Field activities will consist of bridge construction, roadway excavation for ramps, retaining wall excavation, and Limonite Avenue road work.

Lane and Ramp Closures

Contractor will be closing alternating lanes on NB and SB I-15 on Monday through Friday December 3 to December 7 from 9 p.m. to 5 a.m. A minimum of one lane will remain open in each direction at all times.

Construction Update - Week of November 25 - December 1 *STORM UPDATE*

Limonite Progress Schedule 

Contractor will be working on construction stages 1C. Field activities will consist of bridge construction, roadway excavation for ramps, retaining wall excavation, and Limonite Avenue road work.

Lane and Ramp Closures

Contractor will be installing temporary bridge support structures Friday, November 30 and Saturday, December 1. Full freeway closures will be taken as noted on the schedule below. The contractor may have to change closure nights because of the rain forecast for the area over the weekend. Placing the temporary support system over the I-15 freeway will allow the contractor to begin constructing the new south Limonite bridge.

Update: Contractor successfully installed the temporary bridge support in its entirety on Friday night, so no further closures on this notice will be required.

Closure

NB and SB I-15 Full closure

Full closure of Limonite Ave.

NB I-15 Full closure

Full closure of Limonite Ave.

Schedule

Friday night, November 30

9 p.m. to 6 a.m


Saturday night, December 1

9 p.m. to 6 a.m

Construction Update - Week of November 18 - 24

Limonite Progress Schedule 

Contractor will be working on construction stages 1C. Field activities will consist of abutment forming, CIDH pile drilling/pouring, roadway excavation for ramps, retaining wall excavation, and Limonite road work.

Lane and Ramp Closures

The electricians will be installing falsework lighting next Mon & Tue and will be taking a single lane closure and closing a single lane on Limonite Ave. (one direction on Monday, both directions on Tuesday) and perhaps one ramp closure (NB off) on Tuesday. One lane will always remain open on Limonite Ave. in each direction.

Schedule

Monday night to Tuesday night, November 19 - 20
9 p.m. to 5 a.m

Tuesday night, November 20
9 p.m. to 5 a.m



Closure

Single lane closures on Limonite Ave. (one direction on Monday, both directions on Tuesday)

NB Limonite Off-Ramp

Construction Update - Week of October 21 to October 27 **UPDATE**

Limonite Progress Schedule 

Contractor will be working on construction stages 1C. Field activities will consist of abutment forming, CIDH pile drilling/pouring, roadway excavation for ramps, retaining wall excavation, and Limonite road work.

Lane and Ramp Closures

No closures are anticipated this week.

Night of October 26 only. Alternating lane closures on NB and SB i-15. Closure of NB off-ramp from 9 PM to 5 AM.

Emergency Construction Update - October 17 to October 19

Limonite Progress Schedule 

Contractor will be working on construction stages 1C. Field activities will consist of abutment forming, CIDH pile drilling/pouring, roadway excavation for ramps, retaining wall excavation, and Limonite road work.

Lane and Ramp Closures

Night time emergency closure of the NB off-ramp from 9 PM to 5 AM. Closure starting on 10/17 to 10/19.

Schedule

Wednesday night to Friday night, October 17 - 19
9 p.m. to 5 a.m

Closure

NB Limonite Off-Ramp

Construction Update - Week of September 16 - 22 **UPDATE**

** UPDATE** Closures extended to Friday

Limonite Progress Schedule 

Contractor will be working on construction stages 1C. Field activities will consist of south side of bridge demolition, abutment excavation, CIDH pile drilling, shoring, roadway excavation for ramps, retaining wall excavation, and Limonite road work.

Lane and Ramp Closures

Night time alternating lane closures are anticipated for SB and NB Lanes between Cantu Galliano and Sixth Street, between 9 PM and 5 AM. Closures starting 9/17 to 9/19. Night time ramp closures are anticipated as below:

Schedule

Monday night to Friday night, September 17 - 21
9 p.m. to 5 a.m.

Closure

NB / SB Limonite Ramps on and off

Construction Update - Week of September 9 - 15 **UPDATE**

Update: Demolition work was completed Saturday night September 15. There will not be a freeway closure on Sunday night, September 16. Previously scheduled ramp closures are still in effect.

Limonite Progress Schedule 

Contractor started construction on the Limonite Avenue Interchange Project on August 23, 2018. Field activities will consist of demolishing the south side of the Limonite Avenue Bridge over the I-15 freeway.

Lane and Ramp Closures

Monday night, September 10, traffic on Limonite Avenue will be switched to the north side of Limonite Avenue. Traffic will remain in this configuration until the south side of Limonite Bridge is reconstructed.

Full freeway closures along I-15, under the Limonite Avenue Bridge, between 9 PM and 6 AM will be implemented for bridge demolition. Closures will tentatively be 9/14 to 9/15, the Limonite Avenue bridge will be closed to thru traffic. Emergency responders will have access to the Limonite Avenue bridge for emergency use only. Night time closures are anticipated as below:

*Update: The full freeway closures have been moved to Saturday night, September 15 and Sunday night, September 16.

Schedule

Monday night, September 10
9 p.m. to 6 a.m.

Monday to Thursday, September 10-13
9 p.m. to 6 a.m.

Saturday and Sunday, September 15 - 16
9 p.m. to 6 a.m.

Closure

Traffic lanes will be rerouted to the north side of Limonite Avenue with re-striped lane lines and concrete barriers

NB / SB Limonite Ramps on and off
 

Full closure of the I-15 Freeway, full closure of Limonite Avenue Bridge (Bridge access will remain available for Emergency Responders)