Construction Update - Week of June 9 - 15, 2019 Update

Limonite Progress Schedule 

Contractor is working on stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.

Ramp and Street Closures

Contractor will be constructing the temporary bridge supports to build the south side of the Limonite Avenue bridge. Alternating closures of the 2 inside lanes of the I-15 in each direction will occur on Monday night to Thursday night from 9pm to 4am. Full I-15 freeway closure will take place Friday night from 9pm to 4am. Limonite Avenue will also be closed Friday night to facilitate the I-15 Freeway closure detour.

Added Saturday night full Freeway closure

Schedule

Monday to Thursday, June 10 - 13

9pm - 4am

Friday and Saturday, June 14 - 15

9pm - 4am

Closure

Alternating I-15 closures of 2 inside lanes

Full I-15 freeway closure

Full closure of Limonite Avenue