Construction Update - Week of September 22 - 28, 2019

Limonite Progress Schedule 

Contractor is working on Stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.

Ramp and Street Closures

Contractor will be lowering the temporary supports under the bridge and removing portions of the temporary supports that are not over the freeway. Also, work will begin on the connections of Limonite Avenue to the bridge deck.

The eastern temporary entrance to Eastvale Gateway along Limonite Avenue will be closed. The permanent entrance at the same location will be opened when the bridge is opened to it’s final configuration.

Schedule

Monday, September 23
8:00pm - 5:00am

Tuesday - Thursday, September 24 - 26
8:00pm - 5:00am

Closure

15 minute traffic breaks on the I-15 freeway

NB I-15 loop on-ramp closure