Construction Update - Week of October 27 UPDATE
/Limonite Progress Schedule
Contractor is working on Stage 3. Field activities will consist of traffic signal improvements at both intersections, completion of improvements of median island along Limonite Avenue.
Ramp and Street Closures
Contractor will be taking alternating lane closures on Limonite Ave on both Jurupa and Eastvale sides as they slurry seal the asphalt. Due to material specifications this work has to be completed with sunlight and will require daylight closures. During the week night work closures will be taken every night this week. Please see schedule for closures.
**Full closure of EB Limonite Avenue Monday - Friday nights 9pm - 5am**
Schedule
Saturday to Monday, October 26 - 28
Day 9:00am - 5:00pm
Monday to Friday, October 28 - November 2
Night 9:00pm - 5:00am
Closure
Limonite Avenue alternating lane closures
One lane of traffic will be open at all times on the side
being worked on.
WB Limonite Avenue alternating lane closures
EB Limonite Avenue full closure
Full closure all ramps