Construction Update - Week of November 3

Limonite Progress Schedule 

Contractor is working on Stage 3. Field activities will consist of traffic signal improvements at all intersections, completion of improvements of median island along Limonite Avenue.

Ramp and Street Closures

Contractor will be switching traffic to its final configuration throughout the project on Monday night, November 4. The center lanes along Limonite Avenue will be opened. NB on-ramp will also be opened and EB traffic on Limonite Avenue will now turn right to enter the NB I-15 rather then crossing oncoming traffic to use the loop ramp.

The schedule below will show closures for the week.

Schedule

Monday November 4
Night 9:00pm - 5:00am


Tuesday to Wednesday, November 5 - 6
Night 9:00pm - 5:00am


Thursday and Friday, November 7 - 8
Night 9:00pm - 5:00am

Closure

Full closure Limonite Avenue
Full closure all ramps
Alternating lane closures I-15

Alternating lane closures Limonite Avenue
Full closure all ramps
Alternating lane closures I-15

Full closure all ramps
Alternating lane closures I-15