Construction Update - Week of November 10 - 16, 2019
/Limonite Progress Schedule
Contractor is working on Stage 3. Field activities will consist of traffic signal improvements at all intersections, and completion of improvements of median island along Limonite Avenue.
Ramp and Street Closures
Contractor will be grinding lanes placing rock surfaces in landscape areas.
The schedule below will show closures for the week.
Schedule
Tuesday and Wednesday November 12, 13
Night 9:00pm - 5:00am
Thursday and Friday, November 14, 15
Night 9:00pm - 5:00amv
Closure
Full closure all ramps
Alternating lane closures NB and SB I-15
Full closure all ramps
Alternating lane closures SB I-15