Construction Update - Week of July 21 - 27, 2019

Limonite Progress Schedule 

Contractor is working on stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.

Ramp and Street Closures

Contractor will be closing the existing northbound on-ramp and opening the new northbound loop on-ramp. Traffic will be diverted from the existing northbound on-ramp to the new northbound loop on-ramp.

Schedule

Wednesday, July 24 at 5am

Closure

Traffic will be switched from the existing NB on-ramp to the new NB loop on-ramp