Construction Update - Week of July 21 - 27, 2019 *UPDATE*
/Limonite Progress Schedule
Contractor is working on stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.
Ramp and Street Closures
Contractor will be pouring the support structure of the north side of the Limonite Bridge on Monday, July 22. See schedule below for affected traffic lanes.
Contractor will be closing the existing northbound on-ramp and opening the new northbound loop on-ramp. Traffic will be diverted from the existing northbound on-ramp to the new northbound loop on-ramp.
Schedule
Monday, July 22
8:00pm - 5:00am
9:00pm - 5:00am
9:00pm - 4:00am
11:00pm - 4:00am
Wednesday, July 24 at 5am
Closure
Outside WB lane closure on Limonite Ave Bridge
Outside NB I-15 lane closure
Outside SB I-15 lane closure
Middle SB I-15 lane closure
Traffic will be switched from the existing NB on-ramp to the new NB loop on-ramp