Construction Update - Week of July 21 - 27, 2019 *UPDATE*

Limonite Progress Schedule 

Contractor is working on stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.

Ramp and Street Closures

Contractor will be pouring the support structure of the north side of the Limonite Bridge on Monday, July 22. See schedule below for affected traffic lanes.

Contractor will be closing the existing northbound on-ramp and opening the new northbound loop on-ramp. Traffic will be diverted from the existing northbound on-ramp to the new northbound loop on-ramp.

Schedule

Monday, July 22

8:00pm - 5:00am

9:00pm - 5:00am

9:00pm - 4:00am

11:00pm - 4:00am

Wednesday, July 24 at 5am

Closure

Outside WB lane closure on Limonite Ave Bridge

Outside NB I-15 lane closure

Outside SB I-15 lane closure

Middle SB I-15 lane closure

Traffic will be switched from the existing NB on-ramp to the new NB loop on-ramp