Construction Update - August 23 to September 1

Limonite Progress Schedule 

Contractor will start construction of the Limonite Interchange Project on August 23, 2018. Contractor will be working on construction stages 1A and 1B. Field activities will consist of construction area entrance installation, ESA (Environmentally Sensitive Area) fence installing, clearing and grubbing of trees, striping, k-rail placement, excavation and paving for northbound/southbound temporary loop ramps.

Lane and Ramp Closures

Night time alternating lane closures are anticipated for SB and NB Lanes between Cantu Galliano and Sixth Street, between 9 PM and 5 AM. Closures starting 8/23 to 8/30.  Night time ramp closures are anticipated as below:

Schedule

Thursday, August 23
9 p.m. to 5 a.m.

Friday, August 24
9 p.m. to 5 a.m.

Monday, August 27
9 p.m. to 5 a.m.

Tuesday, August 28
9 p.m. to 5 a.m.

Wednesday, August 29
9 p.m. to 5 a.m.

Closure

SB Limonite Ramps on and off
 

NB / SB Limonite Ramps on and off
 

SB Limonite Ramps on and off
 

NB Limonite Ramps on and off
 

NB Limonite Ramps on and off


DETOUR MAP

Detour Map Aug 23.png