Construction Update - Week of September 22 - 28, 2019

Limonite Progress Schedule 

Contractor is working on Stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.

Ramp and Street Closures

Contractor will be lowering the temporary supports under the bridge and removing portions of the temporary supports that are not over the freeway. Also, work will begin on the connections of Limonite Avenue to the bridge deck.

The eastern temporary entrance to Eastvale Gateway along Limonite Avenue will be closed. The permanent entrance at the same location will be opened when the bridge is opened to it’s final configuration.

Schedule

Monday, September 23
8:00pm - 5:00am

Tuesday - Thursday, September 24 - 26
8:00pm - 5:00am

Closure

15 minute traffic breaks on the I-15 freeway

NB I-15 loop on-ramp closure

Construction Update - Week of September 8 - 14, 2019

Limonite Progress Schedule 

Contractor is working on Stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB

loop on-ramp.

Ramp and Street Closures

Contractor will be performing electrical work on the ramp intersections. See schedule below for affected traffic lanes.

Schedule

Monday, September 9
9:00pm - 5:00am

Tuesday, September 10
9:00pm - 5:00am

Wednesday, September 11
9:00pm - 5:00am

Thursday, September 12
9:00pm - 5:00am

Closure

EB Limonite Ave single lane closure
SB On Ramp right turn pocket onto the SB On-ramp

EB Limonite Ave single lane closure
SB On-ramp closure of HOV lane

EB Limonite Ave single lane closure
NB On-ramp right turn pocket onto the NB On-ramp

EB Limonite Ave single lane closure

Emergency Closure Notice - September 3, 2019 UPDATE

1 EB lane of Limonite Avenue has been closed from Pat’s Ranch Road to the NB ramps intersection to find a water leak. There is a high possibility that 2 EB lanes will be closed at 4pm today. IF that happens, EB traffic will be directed onto the inside WB lane leaving one lane open in each direction.

At 9pm tonight, Limonite Avenue will be closed from Pat’s Ranch Road to the NB ramps intersection to all traffic until the emergency issues are resolved. Traffic lanes on the Limonite Avenue Bridge will not be affected. Please use alternate routes.

8:00am September 4: Crews are preparing to pave the work area. Limonite Avenue is expected to be open by 12:30pm today.

Construction Update - Week of August 25 - 31, 2019

Limonite Progress Schedule 

Contractor is working on Stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.

Ramp and Street Closures

Contractor will be pouring the deck of the north side of the Limonite Bridge on Monday, August 26. See schedule below for affected traffic lanes.

Schedule

Monday, August 26

8:00pm - 5:00am

Closure

Limonite Ave at Limonite Ave Bridge

NB I-15 one lane closed

SB I-15 two lanes closed

All ramps

Construction Update - Week of July 21 - 27, 2019 *UPDATE*

Limonite Progress Schedule 

Contractor is working on stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.

Ramp and Street Closures

Contractor will be pouring the support structure of the north side of the Limonite Bridge on Monday, July 22. See schedule below for affected traffic lanes.

Contractor will be closing the existing northbound on-ramp and opening the new northbound loop on-ramp. Traffic will be diverted from the existing northbound on-ramp to the new northbound loop on-ramp.

Schedule

Monday, July 22

8:00pm - 5:00am

9:00pm - 5:00am

9:00pm - 4:00am

11:00pm - 4:00am

Wednesday, July 24 at 5am

Closure

Outside WB lane closure on Limonite Ave Bridge

Outside NB I-15 lane closure

Outside SB I-15 lane closure

Middle SB I-15 lane closure

Traffic will be switched from the existing NB on-ramp to the new NB loop on-ramp

Construction Update - Week of July 21 - 27, 2019

Limonite Progress Schedule 

Contractor is working on stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.

Ramp and Street Closures

Contractor will be closing the existing northbound on-ramp and opening the new northbound loop on-ramp. Traffic will be diverted from the existing northbound on-ramp to the new northbound loop on-ramp.

Schedule

Wednesday, July 24 at 5am

Closure

Traffic will be switched from the existing NB on-ramp to the new NB loop on-ramp

Construction Update - Week of July 14 - 20, 2019

Limonite Progress Schedule 

Contractor is working on stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.

Ramp and Street Closures

Contractor will be closing the southbound off-ramp for 5 days beginning Monday, July 15 at 4am and continuing until Saturday, July 20 at 4am.

Schedule

Monday, July 15 4am to

Saturday, July 20 4am

Closure

Full closure of southbound off-ramp

Construction Update - Week of June 16 - 22, 2019

Limonite Progress Schedule 

Contractor is working on stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.

Ramp and Street Closures

Monday to Friday nights from 9pm - 5am, alternating lane closures to allow crews to work on the temporary bridge supports over the freeway.

Construction Update - Week of June 9 - 15, 2019 Update

Limonite Progress Schedule 

Contractor is working on stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.

Ramp and Street Closures

Contractor will be constructing the temporary bridge supports to build the south side of the Limonite Avenue bridge. Alternating closures of the 2 inside lanes of the I-15 in each direction will occur on Monday night to Thursday night from 9pm to 4am. Full I-15 freeway closure will take place Friday night from 9pm to 4am. Limonite Avenue will also be closed Friday night to facilitate the I-15 Freeway closure detour.

Added Saturday night full Freeway closure

Schedule

Monday to Thursday, June 10 - 13

9pm - 4am

Friday and Saturday, June 14 - 15

9pm - 4am

Closure

Alternating I-15 closures of 2 inside lanes

Full I-15 freeway closure

Full closure of Limonite Avenue

Construction Update - Week of May 26 - June 1, 2019

Limonite Progress Schedule 

Contractor is working on stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.

Ramp and Street Closures

Thursday and Friday nights from 9pm - 5am, the inside 2 lanes on the northbound I-15 will be closed to allow crews to work on the bridge supports in the middle of the freeway.

Construction Update - Week of May 19 - May 24, 2019

Limonite Progress Schedule 

Contractor is working on stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.

Ramp and Street Closures

There are no closures planned for next week. However, some work from this week may be continued into next week due to weather or other unforseen circumstances. If that is the case, there may be night closures of Northbound I-15 inside 2 lanes for some nights. Northbound on-ramp could be closed on Monday and Tuesday nights from 9pm to 4am.

Construction Update - Week of May 13 - May 17, 2019 **Updated**

Limonite Progress Schedule 

Contractor is working on stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.

Ramp and Street Closures

The contractor will be closing the NB on-ramp Monday night through Friday night to facilitate grading in that area.

**Update** Southbound off-ramp will be closed Wednesday - Friday nights from 9pm to 5am. Inside 2 lanes of Northbound I-15 freeway will be closed Wednesday - Friday nights from 11pm to 4am.

Schedule

Monday - Friday, May 13 -17

9pm - 5am

Closure

Full closure of Northbound on-ramp

Construction Update - Week of May 5 - May 11, 2019

Limonite Progress Schedule 

Contractor is working on stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.

Ramp and Street Closures

Contractor will complete the demolition of the old bridge support structures for the north side Limonite Avenue Bridge. Foundations for the support structures of the new bridge are being constructed. The 2 outside lanes of the NB I-15 will be closed Monday night from 9pm to 4am.

Schedule

Monday, May 6 9pm - 4am

Closure

NB I-15 closure of 2 outside lanes

Construction Update - Week of April 28 - May 4, 2019

Limonite Progress Schedule 

Contractor is working on stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.

Ramp and Street Closures

Contractor will continue with the removal of the temporary support structures for the south side Limonite Avenue Bridge. The outside lane of the NB I-15 will be closed Monday night, the outside lane of the SB I-15 will be closed Tuesday night, and the the outside lane of either the NB I-15 or SB I-15 will be closed Wednesday night as needed.

Schedule

Monday, April 29 9pm - 4am

Tuesday, April 30 9pm - 5am

Wednesday, May 1 9pm - 5am

Closure

NB I-15 closure of outside lane

SB I-15 closure of outside lane

closure of NB or SB I-15 outside lane as needed

Construction Update - Week of April 21 - 27, 2019

Limonite Progress Schedule 

Contractor is working on stage 2B. Field activities will consist of construction of the south side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.

Ramp and Street Closures

The demolition of the north side of the Limonite Avenue Bridge will take place on Friday and Saturday night, April 26 and 27, 2019. Limonite Avenue will be closed at 8pm each night. The I-15 will be closed at 9pm on Friday and 8:30pm on Saturday. All closures will end at 8am. See map for detours.

Schedule

Friday, April 26

Saturday, April 27

Closure

Closure of Limonite Avenue 8pm to 8am

Closure of I-15 9pm to 8am

Closure of Limonite Avenue 8pm to 8am

Closure of I-15 8:30pm to 8am

Construction Update - Week of April 7 - 13, 2019 **Revised**

Limonite Progress Schedule 

Contractor is nearing completion of construction stage 2A and is beginning work on Stage 2B. Field activities will consist of construction for portions of the NB on-ramp and SB off-ramp.

Ramp and Street Closures

The 10 day ramp closure is still in effect this week. In addition to that, the NB I-15 will be closed on Friday night from 9pm to 5am along with Limonite Avenue and SB ramps. The SB I-15 will be closed on Saturday night from 9pm to 5am along with Limonite Avenue and NB ramps. The detour for the NB I-15 closure will be to exit at NB I-15 off-ramp and re-enter freeway at NB I-15 on-ramp. The detour for the SB I-15 closure will be to exit at SB I-15 off-ramp and re-enter freeway at SB I-15 on-ramp. Limonite Avenue will be closed Thursday night. Ramp closure detour will use the on- and off-ramps at Cantu-Galleano Ranch Road, and Limonite Avenue closure will use the standard detour along Wineville Avenue, Cantu-Galleano Ranch Road, and Hamner Avenue.

Schedule

Thursday night

April 11 from 9pm to 5am

Friday night

April 12 from 9pm to 5am

Saturday night

April 13 from 9pm to 5am

Closure

Full closure of Limonite Avenue

Full closure of NB I-15

Full closure of Limonite Avenue

Full closure of SB ramps

Full closure of SB I-15

Full closure of Limonite Avenue

Full closure of NB ramps