Construction Update - Week of September 30
/Limonite Progress Schedule
Contractor will be working on construction stages 1C. Field activities will consist of abutment excavation, CIDH pile drilling/pouring, roadway excavation for ramps, retaining wall excavation, and Limonite road work.
Lane and Ramp Closures
No closures are anticipated this week.