Construction Update - Week of January 20 - 26, 2019 **UPDATE**

Limonite Progress Schedule 

Contractor will be working on construction stages 1C. Field activities will consist of bridge construction, roadway excavation for ramps, retaining wall excavation, and Limonite Avenue road work.

Lane and Ramp Closures

Contractor will be closing ramps and Limonite Avenue Bridge on Tuesday, January 22, 2019.

**Due to excessive wind last night, the concrete pour could not be done last night, Tuesday, January 22. The closures have been moved to tonight, Wednesday, January 23 instead.

Schedule

Tuesday night, January 22

9 p.m. to 5 a.m

Closure

Full closure of Limonite Avenue Bridge

Full closure of all ramps