Project Update for Week of March 3, 2019 **Update 2**

Limonite Progress Schedule 

Contractor will be working on construction stage 1C. Field activities will consist of bridge construction, roadway excavation for ramps, retaining wall excavation, and Limonite Avenue road work.

Lane and Ramp Closures

Friday, March 8, CHP will be running 15 minute traffic breaks on the I15 Freeway at Limonite Avenue from 11pm to 5am so that the contractor can remove the temporary wooden supports from the new Limonite Avenue Bridge. The SB on-ramp will also be closed during this time.

** The March 8 closure has been moved to Saturday, March 9.

** The March 9 closure has been moved to Thursday, March 14.