Construction Update - Week of May 26 - June 1, 2019

Limonite Progress Schedule 

Contractor is working on stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.

Ramp and Street Closures

Thursday and Friday nights from 9pm - 5am, the inside 2 lanes on the northbound I-15 will be closed to allow crews to work on the bridge supports in the middle of the freeway.