Limonite Progress Schedule 

Contractor is working on Stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.

Ramp and Street Closures

Contractor will be pouring the deck of the north side of the Limonite Bridge on Monday, August 26. See schedule below for affected traffic lanes.

Schedule

Monday, August 26

8:00pm - 5:00am

Closure

Limonite Ave at Limonite Ave Bridge

NB I-15 one lane closed

SB I-15 two lanes closed