Construction Update - Week of September 8 - 14, 2019

Limonite Progress Schedule 

Contractor is working on Stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB

loop on-ramp.

Ramp and Street Closures

Contractor will be performing electrical work on the ramp intersections. See schedule below for affected traffic lanes.

Schedule

Monday, September 9
9:00pm - 5:00am

Tuesday, September 10
9:00pm - 5:00am

Wednesday, September 11
9:00pm - 5:00am

Thursday, September 12
9:00pm - 5:00am

Closure

EB Limonite Ave single lane closure
SB On Ramp right turn pocket onto the SB On-ramp

EB Limonite Ave single lane closure
SB On-ramp closure of HOV lane

EB Limonite Ave single lane closure
NB On-ramp right turn pocket onto the NB On-ramp

EB Limonite Ave single lane closure