Construction Update - Week of November 18 - 24

Limonite Progress Schedule 

Contractor will be working on construction stages 1C. Field activities will consist of abutment forming, CIDH pile drilling/pouring, roadway excavation for ramps, retaining wall excavation, and Limonite road work.

Lane and Ramp Closures

The electricians will be installing falsework lighting next Mon & Tue and will be taking a single lane closure and closing a single lane on Limonite Ave. (one direction on Monday, both directions on Tuesday) and perhaps one ramp closure (NB off) on Tuesday. One lane will always remain open on Limonite Ave. in each direction.

Schedule

Monday night to Tuesday night, November 19 - 20
9 p.m. to 5 a.m

Tuesday night, November 20
9 p.m. to 5 a.m



Closure

Single lane closures on Limonite Ave. (one direction on Monday, both directions on Tuesday)

NB Limonite Off-Ramp