Construction Update - Week of November 25 - December 1 *STORM UPDATE*

Limonite Progress Schedule 

Contractor will be working on construction stages 1C. Field activities will consist of bridge construction, roadway excavation for ramps, retaining wall excavation, and Limonite Avenue road work.

Lane and Ramp Closures

Contractor will be installing temporary bridge support structures Friday, November 30 and Saturday, December 1. Full freeway closures will be taken as noted on the schedule below. The contractor may have to change closure nights because of the rain forecast for the area over the weekend. Placing the temporary support system over the I-15 freeway will allow the contractor to begin constructing the new south Limonite bridge.

Update: Contractor successfully installed the temporary bridge support in its entirety on Friday night, so no further closures on this notice will be required.

Closure

NB and SB I-15 Full closure

Full closure of Limonite Ave.

NB I-15 Full closure

Full closure of Limonite Ave.

Schedule

Friday night, November 30

9 p.m. to 6 a.m


Saturday night, December 1

9 p.m. to 6 a.m