Construction Update - Week of December 2 - 8

Limonite Progress Schedule 

Contractor will be working on construction stages 1C. Field activities will consist of bridge construction, roadway excavation for ramps, retaining wall excavation, and Limonite Avenue road work.

Lane and Ramp Closures

Contractor will be closing alternating lanes on NB and SB I-15 on Monday through Friday December 3 to December 7 from 9 p.m. to 5 a.m. A minimum of one lane will remain open in each direction at all times.