Construction Update - Week of September 16 - 22 **UPDATE**

** UPDATE** Closures extended to Friday

Limonite Progress Schedule 

Contractor will be working on construction stages 1C. Field activities will consist of south side of bridge demolition, abutment excavation, CIDH pile drilling, shoring, roadway excavation for ramps, retaining wall excavation, and Limonite road work.

Lane and Ramp Closures

Night time alternating lane closures are anticipated for SB and NB Lanes between Cantu Galliano and Sixth Street, between 9 PM and 5 AM. Closures starting 9/17 to 9/19. Night time ramp closures are anticipated as below:

Schedule

Monday night to Friday night, September 17 - 21
9 p.m. to 5 a.m.

Closure

NB / SB Limonite Ramps on and off


DETOUR MAP