Construction Update - Week of January 6 - 12
/Limonite Progress Schedule
Contractor will be working on construction stages 1C. Field activities will consist of bridge construction, roadway excavation for ramps, retaining wall excavation, and Limonite Avenue road work.
Lane and Ramp Closures
Contractor will be closing ramps and outside lanes of the I-15 Freeway on Monday and Tuesday, January 7 - 8, 2019.
Schedule
Monday night, January 7
9 p.m. to 6 a.m
Tuesday night, January 8
9 p.m. to 6 a.m
Closure
NB and SB I-15 closure outside lanes
Full closure of all ramps
NB I-15 closure of outside lane
Full closure of NB ramps