Construction Update - January 15 and 17, 2019 **UPDATE**

Limonite Progress Schedule 

Contractor will be working on construction stages 1C. Field activities will consist of bridge construction, roadway excavation for ramps, retaining wall excavation, and Limonite Avenue road work.

Lane and Ramp Closures

Contractor will be closing ramps and Limonite Avenue Bridge on Tuesday and Thursday, January 15 and 17, 2019. The closures on Thursday January 17, 2019 will only be used if the work is not completed on Tuesday.

*Due to rain, this work cancelled for Tuesday, January 15. The contractor is rescheduling this work for Thursday, January 17 or Tuesday, January 22 weather permitting.

Schedule

Tuesday and Thursday nights, January 15 and 17

9 p.m. to 5 a.m

Closure

Full closure of Limonite Avenue Bridge

Full closure of all ramps