Limonite Progress Schedule 

Contractor is working on Stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.

Ramp and Street Closures

Contractor will be performing various tasks in preparation for opening the new Limonite Avenue Bridge on the night of October 19. See schedule below for the closures for this week.

Schedule

Monday and Tuesday, October 14, 15
9:00pm - 5:00am

Wednesday to Saturday, October 16 - 19
9:00pm - 5:00am

Closure

Two outside lanes of I-15 both directions
SB I-15 on and off ramps closed

Two outside lanes of I-15 both directions
All I-15 Ramps at Limonite Avenue closed
Limonite Avenue full closure