Construction Update - Week of September 29 - October 5, 2019 UPDATE

Limonite Progress Schedule 

Contractor is working on Stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.

Ramp and Street Closures

Contractor will be laying pavement on the north side of Limonite Avenue and on the approaches to the Limonite Avenue Bridge on Saturday and Sunday nights. Limonite Avenue and the I-15 ramps will be closed for this construction work.

**UPDATE Saturday closure begins at 11:00pm**

Schedule

Saturday, October 5
11:00pm - 5:00am

Sunday, October 6
9:00pm - 5:00am

Closure

Limonite Avenue will be closed
I-15 ramps will be closed