Construction Update - March 15, 2019

Limonite Progress Schedule 

Contractor nearing completion of construction stage 1C and beginning work on Stage 1D. Field activities will consist of bridge construction, roadway excavation for ramps, retaining wall excavation, and Limonite Avenue road work.

Ramp and Street Closures

Friday, March 15, CHP will be running 15 minute traffic breaks on the I15 Freeway at Limonite Avenue from 11pm to 5am so that the contractor can remove the temporary wooden supports from the new Limonite Avenue Bridge. The SB on-ramp and Limonite Avenue at the bridge will also be closed during this time.

Schedule

Friday, March 15

Closure

CHP will run 15 minute traffic breaks on the I-15 Freeway

Full closure of Southbound on-ramp

Full closure of Limonite Avenue at the bridge