Construction Update - Week of April 7 - 13, 2019 **Revised**
/Limonite Progress Schedule
Contractor is nearing completion of construction stage 2A and is beginning work on Stage 2B. Field activities will consist of construction for portions of the NB on-ramp and SB off-ramp.
Ramp and Street Closures
The 10 day ramp closure is still in effect this week. In addition to that, the NB I-15 will be closed on Friday night from 9pm to 5am along with Limonite Avenue and SB ramps. The SB I-15 will be closed on Saturday night from 9pm to 5am along with Limonite Avenue and NB ramps. The detour for the NB I-15 closure will be to exit at NB I-15 off-ramp and re-enter freeway at NB I-15 on-ramp. The detour for the SB I-15 closure will be to exit at SB I-15 off-ramp and re-enter freeway at SB I-15 on-ramp. Limonite Avenue will be closed Thursday night. Ramp closure detour will use the on- and off-ramps at Cantu-Galleano Ranch Road, and Limonite Avenue closure will use the standard detour along Wineville Avenue, Cantu-Galleano Ranch Road, and Hamner Avenue.
Schedule
Thursday night
April 11 from 9pm to 5am
Friday night
April 12 from 9pm to 5am
Saturday night
April 13 from 9pm to 5am
Closure
Full closure of Limonite Avenue
Full closure of NB I-15
Full closure of Limonite Avenue
Full closure of SB ramps
Full closure of SB I-15
Full closure of Limonite Avenue
Full closure of NB ramps