Construction Update - Week of April 21 - 27, 2019
/Limonite Progress Schedule
Contractor is working on stage 2B. Field activities will consist of construction of the south side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.
Ramp and Street Closures
The demolition of the north side of the Limonite Avenue Bridge will take place on Friday and Saturday night, April 26 and 27, 2019. Limonite Avenue will be closed at 8pm each night. The I-15 will be closed at 9pm on Friday and 8:30pm on Saturday. All closures will end at 8am. See map for detours.
Schedule
Friday, April 26
Saturday, April 27
Closure
Closure of Limonite Avenue 8pm to 8am
Closure of I-15 9pm to 8am
Closure of Limonite Avenue 8pm to 8am
Closure of I-15 8:30pm to 8am