Construction Update - Week of May 13 - May 17, 2019 **Updated**
/Limonite Progress Schedule
Contractor is working on stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.
Ramp and Street Closures
The contractor will be closing the NB on-ramp Monday night through Friday night to facilitate grading in that area.
**Update** Southbound off-ramp will be closed Wednesday - Friday nights from 9pm to 5am. Inside 2 lanes of Northbound I-15 freeway will be closed Wednesday - Friday nights from 11pm to 4am.
Schedule
Monday - Friday, May 13 -17
9pm - 5am
Closure
Full closure of Northbound on-ramp