Construction Update - Week of May 5 - May 11, 2019

Limonite Progress Schedule 

Contractor is working on stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.

Ramp and Street Closures

Contractor will complete the demolition of the old bridge support structures for the north side Limonite Avenue Bridge. Foundations for the support structures of the new bridge are being constructed. The 2 outside lanes of the NB I-15 will be closed Monday night from 9pm to 4am.

Schedule

Monday, May 6 9pm - 4am

Closure

NB I-15 closure of 2 outside lanes