Construction Update - Week of April 28 - May 4, 2019
/Limonite Progress Schedule
Contractor is working on stage 2B. Field activities will consist of construction of the north side of Limonite Avenue, SB on-ramp, NB off-ramp and portions of the NB loop on-ramp.
Ramp and Street Closures
Contractor will continue with the removal of the temporary support structures for the south side Limonite Avenue Bridge. The outside lane of the NB I-15 will be closed Monday night, the outside lane of the SB I-15 will be closed Tuesday night, and the the outside lane of either the NB I-15 or SB I-15 will be closed Wednesday night as needed.
Schedule
Monday, April 29 9pm - 4am
Tuesday, April 30 9pm - 5am
Wednesday, May 1 9pm - 5am
Closure
NB I-15 closure of outside lane
SB I-15 closure of outside lane
closure of NB or SB I-15 outside lane as needed