Construction Update - Week of January 20 - 26, 2019 **UPDATE**

Limonite Progress Schedule 

Contractor will be working on construction stages 1C. Field activities will consist of bridge construction, roadway excavation for ramps, retaining wall excavation, and Limonite Avenue road work.

Lane and Ramp Closures

Contractor will be closing ramps and Limonite Avenue Bridge on Tuesday, January 22, 2019.

**Due to excessive wind last night, the concrete pour could not be done last night, Tuesday, January 22. The closures have been moved to tonight, Wednesday, January 23 instead.

Schedule

Tuesday night, January 22

9 p.m. to 5 a.m

Closure

Full closure of Limonite Avenue Bridge

Full closure of all ramps

Emergency Closure Notice

Limonite Progress Schedule 

Contractor will be working on construction stages 1C. Field activities will consist of bridge construction, roadway excavation for ramps, retaining wall excavation, and Limonite Avenue road work.

Ramp Closures

The I-15 Southbound off-ramp has been closed due to flooding. More rain is expected this afternoon, so the ramp closure is likely to continue throughout the night. The ramp will be reopened as soon as the flooding is alleviated.

Schedule

Thursday, January 17

until flooding is alleviated

Closure

Full closure of Southbound off-ramp

Construction Update - January 15 and 17, 2019 **UPDATE**

Limonite Progress Schedule 

Contractor will be working on construction stages 1C. Field activities will consist of bridge construction, roadway excavation for ramps, retaining wall excavation, and Limonite Avenue road work.

Lane and Ramp Closures

Contractor will be closing ramps and Limonite Avenue Bridge on Tuesday and Thursday, January 15 and 17, 2019. The closures on Thursday January 17, 2019 will only be used if the work is not completed on Tuesday.

*Due to rain, this work cancelled for Tuesday, January 15. The contractor is rescheduling this work for Thursday, January 17 or Tuesday, January 22 weather permitting.

Schedule

Tuesday and Thursday nights, January 15 and 17

9 p.m. to 5 a.m

Closure

Full closure of Limonite Avenue Bridge

Full closure of all ramps

Construction Update - Week of January 6 - 12

Limonite Progress Schedule 

Contractor will be working on construction stages 1C. Field activities will consist of bridge construction, roadway excavation for ramps, retaining wall excavation, and Limonite Avenue road work.

Lane and Ramp Closures

Contractor will be closing ramps and outside lanes of the I-15 Freeway on Monday and Tuesday, January 7 - 8, 2019.

Schedule

Monday night, January 7

9 p.m. to 6 a.m

Tuesday night, January 8

9 p.m. to 6 a.m

Closure

NB and SB I-15 closure outside lanes

Full closure of all ramps

NB I-15 closure of outside lane

Full closure of NB ramps

Construction Update - Week of December 2 - 8

Limonite Progress Schedule 

Contractor will be working on construction stages 1C. Field activities will consist of bridge construction, roadway excavation for ramps, retaining wall excavation, and Limonite Avenue road work.

Lane and Ramp Closures

Contractor will be closing alternating lanes on NB and SB I-15 on Monday through Friday December 3 to December 7 from 9 p.m. to 5 a.m. A minimum of one lane will remain open in each direction at all times.

Construction Update - Week of November 25 - December 1 *STORM UPDATE*

Limonite Progress Schedule 

Contractor will be working on construction stages 1C. Field activities will consist of bridge construction, roadway excavation for ramps, retaining wall excavation, and Limonite Avenue road work.

Lane and Ramp Closures

Contractor will be installing temporary bridge support structures Friday, November 30 and Saturday, December 1. Full freeway closures will be taken as noted on the schedule below. The contractor may have to change closure nights because of the rain forecast for the area over the weekend. Placing the temporary support system over the I-15 freeway will allow the contractor to begin constructing the new south Limonite bridge.

Update: Contractor successfully installed the temporary bridge support in its entirety on Friday night, so no further closures on this notice will be required.

Closure

NB and SB I-15 Full closure

Full closure of Limonite Ave.

NB I-15 Full closure

Full closure of Limonite Ave.

Schedule

Friday night, November 30

9 p.m. to 6 a.m


Saturday night, December 1

9 p.m. to 6 a.m

Construction Update - Week of November 18 - 24

Limonite Progress Schedule 

Contractor will be working on construction stages 1C. Field activities will consist of abutment forming, CIDH pile drilling/pouring, roadway excavation for ramps, retaining wall excavation, and Limonite road work.

Lane and Ramp Closures

The electricians will be installing falsework lighting next Mon & Tue and will be taking a single lane closure and closing a single lane on Limonite Ave. (one direction on Monday, both directions on Tuesday) and perhaps one ramp closure (NB off) on Tuesday. One lane will always remain open on Limonite Ave. in each direction.

Schedule

Monday night to Tuesday night, November 19 - 20
9 p.m. to 5 a.m

Tuesday night, November 20
9 p.m. to 5 a.m



Closure

Single lane closures on Limonite Ave. (one direction on Monday, both directions on Tuesday)

NB Limonite Off-Ramp

Construction Update - Week of October 21 to October 27 **UPDATE**

Limonite Progress Schedule 

Contractor will be working on construction stages 1C. Field activities will consist of abutment forming, CIDH pile drilling/pouring, roadway excavation for ramps, retaining wall excavation, and Limonite road work.

Lane and Ramp Closures

No closures are anticipated this week.

Night of October 26 only. Alternating lane closures on NB and SB i-15. Closure of NB off-ramp from 9 PM to 5 AM.

Emergency Construction Update - October 17 to October 19

Limonite Progress Schedule 

Contractor will be working on construction stages 1C. Field activities will consist of abutment forming, CIDH pile drilling/pouring, roadway excavation for ramps, retaining wall excavation, and Limonite road work.

Lane and Ramp Closures

Night time emergency closure of the NB off-ramp from 9 PM to 5 AM. Closure starting on 10/17 to 10/19.

Schedule

Wednesday night to Friday night, October 17 - 19
9 p.m. to 5 a.m

Closure

NB Limonite Off-Ramp